Subcontractor's shutdown delays enclosure of $825M N.Y. arena

03/1/2012 | Engineering News-Record

The temporary shutdown of ASI Ltd. in January was "untimely" as it was to have made and installed the steel facade panels for the $825 million Barclays Center arena under construction in Brooklyn, N.Y. However, all involved in the project, including prime contractor Hunt Construction Group, are working to keep the project moving by installing temporary enclosures instead. Hunt says it is "confident that we will complete the project as scheduled."

View Full Article in:

Engineering News-Record

Published in Brief: