American Bridge/Fluor complete load transfer on $6.3B Bay Bridge

American Bridge/Fluor crews at work on the $6.3 billion Bay Bridge in California have moved the 35,200-ton single-tower suspension span from temporary supports and attached it to 200 suspension cables. The bridge is scheduled to open by Labor Day. "Completion of the load transfer led to a big collective sigh of relief from all the engineers," Metropolitan Transportation Commission Executive Director Steve Heminger said.

View Full Article in:

San Francisco Chronicle · KPIX-TV (San Francisco) · KGO-TV (San Francisco)

Published in Briefs: