The second structural mat -- which used 1,000 cubic yards of concrete -- was set in place on Thursday at the Medical Mart project in Cleveland, and excavation is starting for micro-pile concrete caps. The first of 30 120-foot-long trusses has been put in place. However, the project hit a snag when workers realized they would have to spend $1.6 million to repair a service road that will be used by construction vehicles.