11/6/2012

Construction work on the Pinnacle Bank Arena in Lincoln, Neb., is 50% finished. The project has used 25,000 cubic yards of concrete, 2,500 tons of steel structure and crews are currently installing the four main roof trusses. The arena has created jobs for 250 workers and is on track to be completed for its fall 2013 opening.