11/25/2013

More than 22.9 million hours of work has gone into construction of the Tennessee Valley Authority's Unit 2 reactor at the Watts Bar Nuclear Power Plant in Tennessee and work is about 80% complete, according to this article. TVA asked for another nine-month extension of its construction permit and the Nuclear Regulatory Commission approved it. Remaining work includes "system completion" and testing. Commercial operation is expected to begin in December 2015.

Related Summaries