Welcome back to CodeWatch, SmartBrief’s monthly examination of the latest codes and standards affecting the built environment.
October was a month of rules catching up to what is already built and plugged in. Some of the movement came from regulators with deadlines. Some came from standards committees working on schedules of their own.
NERC clears reliability standards for data centers
The North American Electric Reliability Corporation’s proposed standards for large data centers recently passed a final industry ballot. The package has three new standards covering interconnection studies and modeling, operational data and communications, and protection coordination and disturbance monitoring. It also proposes revisions to two existing interconnection standards to head off overlap, POWER magazine reported.
The standards would apply to sites with at least 50 megawatts of connected load served at 100 kilovolts or higher. NERC raised that line from the 20 megawatts and 60 kilovolts it first floated after stakeholder comments. A week earlier, its board approved proposed rule changes that would create two new registered entity types, computational load owner and computational load operator. Existing sites would get 36 months to meet disturbance recording requirements. New sites would have until 15 months after the standard takes effect or their in-service date, whichever is later. Owners would also have to verify their dynamic models within 180 days of any equipment or settings change that alters a site’s dynamic response.
The package sets no minimum voltage and frequency ride-through requirements, which NERC is handling in separate work. The standards still need board adoption and a filing at the Federal Energy Regulatory Commission by Dec. 31, as FERC ordered in July.
Separately, ride-through rules for inverter-based resources were set to become mandatory Oct. 1 under NERC’s PRC-029, which draws on IEEE 2800-2022. The first tier covers plants larger than 75 MVA connected at 100 kV or higher. Plants larger than 20 MVA at 60 kV or higher follow Jan. 1, 2027, according to the IEEE Power & Energy Society.
NRC proposes another rewrite of reactor rules
The Nuclear Regulatory Commission has proposed a broad rewrite of its reactor licensing, decommissioning and oversight rules. The Sept. 11 proposal amends nine parts of Title 10 of the Code of Federal Regulations, law firm Orrick reported.
Most of the changes are technical. The NRC would apply the lighter financial qualification standard from its new Part 53 to Parts 50 and 52, and it would end the 15-year expiration on future standard design approvals. Many near-term projects, from small modular reactors to AP1000 builds, will still be licensed under those older parts, Orrick noted.
The rule is one of 23 the agency has started since a May 2025 executive order called for reform of the NRC. The agency has been taking comments under Docket NRC-2025-1138.
The NRC’s commissioners were also scheduled to meet their counterparts at the Federal Energy Regulatory Commission on Oct. 22 at NRC headquarters. NERC’s chief engineer, Mark Lauby, was due to brief both groups on data center registration and reliability standards. The two agencies have held these joint meetings for two decades, FERC said.
FERC proposes blanket authorizations for LNG plants
FERC voted unanimously Oct. 15 to propose a blanket authorization program for liquefied natural gas facilities. Eligible work at LNG plants could proceed without a case-specific order under the Natural Gas Act. The program is modeled on the blanket certificate program FERC has run for interstate pipelines for 40 years, the agency said.
The proposal sorts work into three tiers. Activities that add no capacity, expand no authorized extents and push nothing past design limits would be authorized automatically. Work that could add capacity inside the existing footprint would need 60 days’ notice. New liquefaction trains, tanks and marine berths would need 90 days’ notice, with limits on facility type, location and size.
FERC also proposes standard environmental and engineering design conditions for projects approved this way. Engineers will want to read them closely, since they would become the checklist for work that skips a case-by-case order. Comments are due 60 days after the proposal appears in the Federal Register.
A companion item deals with air quality reviews. Under a draft policy statement, FERC would stop asking applicants for gas projects to supply air dispersion modeling for its environmental reviews. Comments on that one are due Nov. 16.
The 2027 I-Codes arrive as states finish the 2024 cycle
The 2027 International Building Code is on the market. The International Code Council lists it as available in digital format, with print editions due in late October.
The new edition lets some four-story Group R-2 buildings use one exit when specific safeguards are met. That is the single-stair question Chicago aldermen weighed earlier this year.
Flood and wind rules tighten as well. Flood hazard areas expand to the 500-year floodplain, with elevation and load requirements tied to risk category. The windborne debris definition now matches ASCE 7-22.
Energy storage gets more attention. The code spells out where sprinklers are required for lithium-ion and lithium metal battery storage. The International Fire Code adds a new Chapter 43 for batteries and battery-powered equipment, which greatly expands battery storage requirements, ICC says.
Factory-built housing drew federal attention too, on top of the ICC/MBI off-site standards the 2027 codes now reference. An Oct. 22 executive order created a Task Force on Manufactured Housing Innovation, co-chaired by the housing secretary and the Federal Housing Finance Agency director.
The task force has 180 days to recommend ways to cut duplicative federal reviews and have agencies recognize one another’s inspections and approvals for factory-built housing. It is also to weigh whether federal grants could encourage states and localities to adopt standardized permitting for such housing, the order says.
The rest of the family arrives in stages. ICC’s store lists the 2027 residential code for late January. ICC is targeting Dec. 1 for the 2027 energy code.
States are still finishing the last cycle. Florida’s 9th Edition code, built on the 2024 I-Codes, takes effect Dec. 31. Washington’s State Building Code Council targeted Oct. 16 for final adoption of its 2024 amendments, with an effective date of May 3, 2027. Oklahoma’s rules adopting the 2024 building and existing building codes took effect Sept. 14. The 2027 editions will be waiting.
Product category rules reach HVAC and the 2029 NEC takes shape
ASHRAE opened public review Oct. 2 on a proposed standard for writing product category rules for HVAC&R-related mechanical, electrical and plumbing products. Standard 244P would guide the life cycle assessments and environmental product declarations built on those rules. Comments are due Dec. 1, ASHRAE said.
Last month’s column covered the concrete industry’s updated rule. The HVAC side now has a draft of its own. ASHRAE also opened review of Guideline 1.6P on commissioning data centers, with comments due Nov. 16.
Work on the 2029 National Electrical Code has moved from public input to first draft. The National Fire Protection Association’s code-making panels met Sept. 22 through Oct. 3. The first draft report is due June 10, 2027, and public comment on it closes July 29, according to the cycle schedule posted by the RV Industry Association.
ASTM tackles tests for sites and materials
ASTM International approved a guide for detailed karst investigations at development sites. The standard, D8658/D8658M, applies when a preliminary survey under D8512 shows karst features could affect or be affected by a project. Together the two help developers decide whether to build on a site with sinkholes, caves or soluble bedrock, and how, according to ASTM member Robert Denton.
A separate committee is working on a test for how insulation systems resist creep. D09, the committee on electrical insulating materials, is developing D8687, which measures the surface breakdown voltage of solid insulation in an insulating liquid so creep strength can be compared under controlled conditions. It is useful to makers of the insulating materials and of liquid-filled equipment where creep stresses run high. The setup forces a creep failure along the material’s surface while eliminating interferences, such as oil wedges, that could produce lower readings, said ASTM member Brad Greaves of Weidmann Electrical Technology.
The plastics committee wants a faster weathering test for polycarbonate and polyester blends used in buildings, car parts and electrical enclosures. Proposed standard WK97238 aims to predict outdoor durability in the lab. Current tests are slow, costly and poor predictors of color and gloss changes, which produces false pass and fail results, said ASTM member Olga Kuvshinnikova. The test is not expected to work well for polyethylene and polypropylene, and the committee is looking for volunteers.
__________________________________________________________________________________________
If you sit on a code or standards committee and would like to have your work featured in the next CodeWatch, email Evan Milberg at [email protected]. For more news updates on the latest codes and standards shaping the built environment and energy sectors, sign up for one or more of SmartBrief’s infrastructure newsletters today.