Tokyo Electric Power is now estimating that it will take 12 years and $12.6 billion to remove the melted nuclear fuel from two of the three damaged reactors at the Fukushima Daiichi Nuclear Power Plant. TEPCO has not yet estimated the removal cost for the third reactor, Unit 1, for which no plan has been developed.